1. STRUCTURE: R.C.C framed structure with Brick/ Solid Block/ Cement Block walls plastered and finished with Two Coats of Cement based Putty, with one coat of primer and two coats of Asian Premium Emulsion/Equivalent. Ceiling surfaces inside the apartments will be given one coat of cement paint on the RCC surface and 12mm gypsum board false ceiling with galvinised iron section supports. Joints will be taped with touchup putty and finished with one coat of primer and two coats of White colour Premium Emulsion.
2 JOINERY:
a. Main door: First Quality African Teak both frame and shutters (Panel door) Polished both sides with melamine spray.
b. Other doors: will be deep-moulded compressed wood fibre raised panel doors, strengthened with pre-selected kiln dried rails and stiles, with a grain effect etched in the panel with first quality teak frames, painted on both sides. All door frames will be teak frames. Toilet doors will be prepainted ABS doors.
c. Windows: All windows will be UPVC windows, with 5mm glazed shutters and Bright Bar grills embedded in the wall.
d. Ventilator: Toilet ventilators will be with aluminium adjustable louvers with inbuilt provision for exhaust fan.
3. FLOORING:
a. Flooring for the Living/ Dining area alone will be laid with 4x2 KAJARIA/ equivalent tiles @ Rs.100/Sft.
b. Vitrified tile flooring (24” x 24”) from Nitco/ Asian/ Equivalent plain colours @ Rs.50/Sft, for the rest of the flat (all bedrooms, kitchen, balconies and passages) with 4” high skirting.
4. KITCHEN: Polished Black galaxy granite slab over cooking platform, NIRALI/ equivalent Stainless steel sink with drain board and plain glazed tiles (10 x 16) upto 2’ height above the platform. Black Granite slabs will be provided for the kitchen shelves.
5. TOILETS: Plain ceramic tile flooring, ceramic printed/ plain tile dado, for about 7’0” height from floor, concealed plumbing arrangements.
6. SANITARYWARES & FIXTURES: PARRYWARE/ CERA equivalent wall mounted model White closets with concealed tank provided in all bathrooms. Half turn foam flow taps and fittings KOHLER or Equivalent for all toilets. Each toilet shall be provided with one water closet, one wash basin, one single lever divertor, One tipton and shower rose, one health faucet, pillar cock & angle valve for wash basin and 20 mm concealed stop cock. A towel rod and 12”glass corner soap tray will be provided in each toilet.
7. ELECTRICAL: Three phase electric supply connection with a separate Manual Three phase changeover switches inside each flat and wiring will be of copper fire retardant cables concealed in PVC conduits. MINIATURE CIRCUIT BREAKERS & RCCB (Residual Current Circuit Breaker) will be provided and switches will be Modular Type mounted on metal boxes from LEGRAND/ EQUIVALENT. Provision for A/C in all bedrooms.
8. CHEMICAL EARTHING done for the building by digging 3m deep bores inserted with hot dipped galvanized dual pipes, filled with high conductive and corrosion resistant crystalline mixture and backfill compound around the electrodes.
9. WATER SUPPLY: Corporation and borewell water supply in the kitchen, service and bathrooms. A common pressure booster pump will be provided for the project.
10.LIFT: A SIX Passenger AUTO DOORLIFTwill be provided from EMPEROR/ Equivalent.
11. GENERATOR
Standby Generator with alternator, sound proof enclosure, control panel, change over panel and earthing etc., will be provided to support the lift, common area lights, motors, and only lights & fan points inside the flats
12. Special weather proofing treatment will be done to the mother terrace to reduce the heat on the top floor.
FLOOR | FLAT | AREA ( IN SQ. FEET) | AVAILABILITY |
---|---|---|---|
First Floor | Flat on the 1st Floor | 1254 Sq.Ft | |
Second Floor | Flat on the 2nd Floor | 1254 Sq.Ft | |
Third Floor | Flat on the 3rd Floor | 1254 Sq.Ft | |
Fourth Floor | Flat on the 4th Floor | 1254 Sq.Ft |
PAYMENT SCHEDULE | |
---|---|
At the time of BOOKING | 30% |
On completion of BASEMENT | 12% |
On completion of GROUND FLOOR ROOF | 10% |
On completion of FIRST FLOOR ROOF | 10% |
On completion of SECOND FLOOR ROOF | 10% |
On completion of THIRD FLOOR ROOF | 10% |
On completion of FOURTH FLOOR ROOF | 10% |
On completion of BRICK WORK of your flat | 5% |
On HANDING OVER POSSESSION | 3% |